AMFP Upper Midwest Healthcare On-Site Prefabrication
About this event
For the construction of Bon Secours Mercy Health’s Kings Mills Hospital, the Contractor built a temporary structure that contained two prefabrication lines.
The Contractor reported a savings of 5 months from what was originally a 27-month construction duration by improving on-site labor utilization by 81%. This presentation will give an overview of the project and how the project delivery team had to adjust their typical delivery practices to ensure success of this delivery concept.
Category
AMFP Upper Midwest
Registration Info
Registration is required
Payment In Full In Advance Only
Number of People Who Will Attend
If you are a member, please log in to access additional, potentially lower registration fee options.
Search for your information - enter the following
* This can be your primary registrant type. Only one primary registrant type is allowed per registration.
Invalid Quantity
Register Now